SPEED and Reliability Act of 2025
Introduced
In committee
Current stepReported
Not yetPassed House
Not yetPassed Senate
Not yetResolving differences
Not yetSent to the president
Not yetSigned
Not yetBecame law
Not yet
AI-generated from the official bill text and not reviewed by a person. It may contain errors. How summaries are made
The SPEED and Reliability Act of 2025 would amend the Federal Power Act to revise how the Federal Energy Regulatory Commission permits, coordinates, and allocates the costs of interstate electric transmission facilities.
Who it affects
Electric transmitting utilities, energy customers, landowners (including farmers and ranchers along proposed transmission paths), Indian Tribes, state utility commissions, the Federal Energy Regulatory Commission, and the Department of the Interior. It specifically excludes utilities operating solely within the ERCOT grid.
Based on the Introduced in House text · gemini-3.8-flash
Generated October 6, 2026 · Read the official text on Congress.gov
Your Vote
1 key actions of 2: Congress.gov's major actions and roll-call votes.
Introduced in House
Recorded by: Library of Congress
Sections of law the bill's Introduced in House text would amend, repeal or add to, found in the bill's own text. US Code current through Public Law 119-142.
- Amends
16 U.S.C. 824p
Siting of interstate electric transmission facilities
No AI explanation of this change yet.
The bill's instruction
Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (a) and inserting the following: “ (a) Definitions In this section: (1) Commission The term Commission means the Federal Energy Regulatory Commission. (2) ERO The term ERO has the meaning given such term in section 215(a). (3) Improved reliability The term improved reliability means that, on balance, considering each of the matters described in subparagraphs (A) through (D), reliability is improved in a material manner that benefits customers through at least one of the following: (A) Facilitating compliance with a mandatory standard for reliability approved by the Commission under section 215. (B) A reduction in expected unserved energy, loss of load hours, or loss of load probability (as defined by the ERO). (C) Facilitating compliance with a tariff requirement or process for resource adequacy on file with the Commission. (D) Any other similar material improvement, including a reduction in correlated outage risk, such as achieved through increased geographic or resource diversification. (4) Landowner input The term landowner input means input received— (A) by the Commission; (B) from affected landowners, such as farmers and ranchers, in the path of the proposed construction or modification of an electric transmission facility; and (C) pursuant to notification provided to, and consultation with, those affected landowners, farmers, and ranchers by the Commission. (5) Secretary The term Secretary means the Secretary of Energy. .” Section 216(b) of the Federal Power Act (16 U.S.C. 824p(b)) is amended— (1) in the matter preceding paragraph (1), by striking “Except” and all that follows through “finds that” and inserting “Except as provided in subsections (d)(1) and (i), the Commission shall, after notice and an opportunity for hearing, including a public comment period of at least 60 days, issue one or more permits for the construction or modification of electric transmission facilities necessary in the national interest if the Commission finds that”; (2) in paragraph (1)— (A) in subparagraph (A)(i), by inserting “or modification” after “siting”; and (B) in subparagraph (C)— (i) in the matter preceding clause (i), by inserting “or modification” after “siting”; and (ii) in clause (i), by striking “the later of” in the matter preceding subclause (I) and all that follows through the semicolon at the end of subclause (II) and inserting “the date on which the application was filed with the State commission or other entity;”; and (3) by striking paragraphs (2) through (6) and inserting the following: “ (2) the proposed facilities will be used for the transmission of electric energy in interstate (including transmission from the outer Continental Shelf to a State) or foreign commerce; (3) the proposed construction or modification is consistent with the public interest; (4) the proposed construction or modification will significantly reduce transmission congestion in interstate commerce, protect or benefit consumers, and provide improved reliability; (5) the proposed construction or modification is consistent with sound national energy policy and will enhance energy independence; (6) the electric transmission facilities are capable of transmitting electric energy at a voltage of not less than 100 kilovolts or, in the case of facilities that include advanced transmission conductors (including superconductors), as defined by the Commission, voltages determined to be appropriate by the Commission; and (7) the proposed modification (including reconductoring) will maximize, to the extent reasonable and economical, the transmission capabilities of existing towers, structures, or rights-of-way. .” Section 216(e)(3) of the Federal Power Act (16 U.S.C. 824p(e)(3)) is amended by striking “shall conform” and all that follows through the period at the end and inserting “shall be in accordance with rule 71.1 of the Federal Rules of Civil Procedure.”.
Also changed by S. 5653, H.R. 10539, H.R. 10302, S. 4765, H.R. 8248
- Amends
16 U.S.C. 824s
Transmission infrastructure investment
Subsections (b)(4)
No AI explanation of this change yet.
The bill's instruction
Section 219(b)(4) of the Federal Power Act (16 U.S.C. 824s(b)(4)) is amended— (1) in subparagraph (A), by striking “and” after the semicolon at the end; (2) in subparagraph (B), by striking the period at the end and inserting “; and”; and (3) by adding at the end the following: “ (C) all prudently incurred costs associated with payments to jurisdictions impacted by electric transmission facilities developed pursuant to section 216. .”
Also changed by S. 5653, H.R. 8568, H.R. 7977, H.R. 7729, S. 3947
- Amends
42 U.S.C. 16421
Third-party finance
No AI explanation of this change yet.
The bill's instruction
Section 1222 of the Energy Policy Act of 2005 (42 U.S.C. 16421) is amended— (A) in subsection (a)(1)(A), by striking “is located in a national interest electric transmission corridor designated under section 216(a) of the Federal Power Act and”; and (B) in subsection (b)(1)(A), by striking “is located in an area designated under section 216(a) of the Federal Power Act and”.
- Amends
42 U.S.C. 18713
Transmission facilitation program
Subsections (h)(1)(A)
No AI explanation of this change yet.
The bill's instruction
Section 40106(h)(1)(A) of the Infrastructure Investment and Jobs Act (42 U.S.C. 18713(h)(1)(A)) is amended by striking “(A) is located in” and all that follows through “(B) is necessary” in subparagraph (B) and inserting “is necessary”.
Also changed by S. 5653, S. 3976, H.R. 7728, H.R. 7043, H.R. 2347
- Amends
42 U.S.C. 18715
Transmission facility financing
Subsections (b)
No AI explanation of this change yet.
The bill's instruction
Section 50151(b) of Public Law 117–169 (42 U.S.C. 18715(b)) is amended by striking “designated by the Secretary to be necessary in the national interest under section 216(a) of the Federal Power Act (16 U.S.C. 824p(a))”.